Things to Know: CalTrain Construction Update

Caltrain Construction and Maintenance: July 20 to July 26, 2013

San Bruno Grade Separation Project

Day work will be done from 7 a.m. to 6 p.m. This week, crews will continue painting the exterior and installing the Huntington elevator. Crews also will install power and lighting, and continue work on the Sylvan Pedestrian Tunnel. 

Starting on 8 p.m. Monday, July 22, until 5 a.m. Saturday July 27, Angus Avenue will be closed due to construction.  Crews will be excavating and removing portions of the roadway to lower streets and allow for greater vehicular clearance under the crossings. Once completed, the clearance for the intersection will be approximately 15 feet.

During the closure, Caltrain will establish detour signs for pedestrians and motorists to help with traffic flow. The closure has been coordinated with emergency services. Night work will be done in accordance with Caltrain and city agreements and ordinances. We apologize for any inconvenience this may cause you.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues.  A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue. Work on this project will not disrupt Caltrain service.

Find out what's happening in San Brunowith free, real-time updates from Patch.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Maintenance

Find out what's happening in San Brunowith free, real-time updates from Patch.

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. This work will not disrupt Caltrain service. For more information about this type of work, click here.

San Francisco to San Jose
Saturday, July 20, through Friday, July 26, crews will power wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations. Sunday, July 21, to Friday, July 26, crews will clean-up the right of way between San Francisco and Tamien stations from 6 a.m. to 3 p.m. 

San Francisco to Millbrae
Monday, July 22, to Wednesday, July 24, crews will remove and replace ties between Bayshore and Millbrae stations. 

South San Francisco
On Sunday, July 21, crews will remove and replace ties around the South San Francisco station. 

Construction Outreach Hotline: 650.508.7726