Things To Know: Caltrain Grade Separation Update

Caltrain Construction and Maintenance: July 27 to Aug. 2, 2013

July 26, 2013

Construction

San Bruno Grade Separation Project

Find out what's happening in San Brunowith free, real-time updates from Patch.

Day work will be done from 7 a.m. to 6 p.m. This week, crews will continue painting the exterior and installing the Huntington elevator. Crews also will install handrails and continue work on the Euclid Tunnel. 

Crews will continue excavating and removing portions of the roadway on Angus Avenue until 5 p.m. Saturday, July 27, to lower streets and allow for greater vehicular clearance under the crossings. Once completed, the clearance for the intersection will be approximately 15 feet.

During the closure, Caltrain will establish detour signs for pedestrians and motorists to help with traffic flow. The closure has been coordinated with emergency services. Night work will be done in accordance with Caltrain and city agreements and ordinances. We apologize for any inconvenience this may cause you.

Find out what's happening in San Brunowith free, real-time updates from Patch.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues.  A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue. Work on this project will not disrupt Caltrain service.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. This work will not disrupt Caltrain service. For more information about this type of work, click here.

San Francisco to San Jose
Saturday, July 27, through Friday, Aug. 2, crews will power wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations. 

San Francisco
Monday, July 29, to Thursday, Aug. 1, crews will be conducting signal maintenance and testing around 22nd Street station as part of the Signal Rehabilitation Project. 

San Francisco to San Bruno
Monday, July 29, to Thursday, Aug. 1, crews will remove and replace ties between the Bayshore and San Bruno stations. 

San Francisco to Millbrae
On Sunday, July 28, crews will remove and replace ties between the Bayshore and Millbrae stations. 

Millbrae
Night work to resurface the tracks and other maintenance work around Santa Paula Avenue, adjacent to Hemlock Avenue and Monterey Street, has been delayed until Aug. 5. 

Redwood City to Mountain View
Wednesday, July 31, and Thursday, Aug.  1, crews will resurface tracks between the Redwood City and San Antonio stations. 

Menlo Park to Sunnyvale
Sunday, July 28, to Tuesday, July 30, crews will resurface tracks between the Menlo Park and Sunnyvale stations.

San Jose
Sunday, July 28, crews will weld and grind tracks around the Tamien station. Also, Monday, July 29, to Thursday, Aug. 1, crews will weld and grind tracks between College Park and Diridon stations. 