This post was contributed by a community member. The views expressed here are the author's own.

Community Corner

Things to Know: San Bruno Grade Separation Update

San Bruno Grade Separation



Overview

The $147 million San Bruno Grade Separation Project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. This will improve safety for both motorists and pedestrians, and it will reduce traffic congestion to and from Highway 101 in the City of San Bruno.

In addition, a new elevated Caltrain station will be constructed between San Bruno and San Mateo avenues, replacing the existing station at Sylvan Avenue. A total of 201 parking spaces and a “kiss and ride” lot will serve the station at the site of the former San Bruno Lumber.

With respect to pedestrian safety and amenities, the project will provide three pedestrian underpasses - one in the vicinity of Sylvan Avenue, one at the new station and another between Euclid Avenue and Walnut Street. Additionally, elevators will provide easy access for Caltrain customers. Streets and sidewalks, including those at Posy Park, also will be improved.

Construction Updates

Day work will be done from 7 a.m. to 6 p.m. This week, crews will continue painting the exterior, installing handrails in the Sylvan pedestrian tunnel, and working on the San Mateo and San Bruno bridge platforms. 

During the month of September, road closures will occur on San Mateo and San Bruno avenues. Construction crews will continue excavating and removing portions of the roadway to lower streets and allow for greater vehicular clearance under the crossings. Once completed, the clearance for the intersection will be approximately 15 feet. Road work at Angus Avenue was completed at the end of July. Due to unforseen utility issues, the road closure schedule has been pushed back. The following is an update list of road closure times and dates:

• San Mateo Avenue, between Huntington and San Bruno avenues, will be closed from 8 p.m. Friday, Sept. 6, until 5 a.m. Monday, Sept. 9.

• San Bruno Avenue, between First and Huntington avenues, will be closed on two separate occasions. The first portion of the work will require partial closure of the street from 8 p.m. Friday, Sept. 13, until 5 a.m. Monday, Sept. 16. The second portion will completely shut down San Bruno Avenue at Huntington Avenue. That closure is scheduled for 8 p.m. Friday, Sept. 20, until 5 a.m. Monday, Sept. 30.

During the closures, Caltrain will establish detour signs for pedestrians and motorists to help with traffic flow. During the full shutdown of San Bruno Avenue, electronic signs will be displayed on San Bruno Avenue and on El Camino Real directing traffic around the closure.  Night work will be done in accordance with Caltrain and city agreements and ordinances. We apologize for any inconvenience this may cause you.

Upcoming Community Meeting:

Please join us for a community meeting regarding the San Bruno Grade Separation Project. The meeting will include project updates, landscaping information along the east side of First Avenue and an updated street closure schedule.  There also will be an opportunity to address questions from the community.

Find out what's happening in San Brunowith free, real-time updates from Patch.

This meeting will be held at 6 p.m. Wednesday, Sept. 4, 2013 at the following location:
Belle Air Elementary School, 450 Third Ave., San Bruno

In addition, Caltrain will also introduce installation details of the CBOSS/PTC Project, an advanced signal system that will equip the corridor with federally-mandated safety technology and will increase system capacity to help accommodate future ridership demand. 

PROJECT PHOTOS

Project Documents & Notices
Updated - Road Closure Map - Aug. 29, 2013
Community Meeting Notice - Aug. 26, 2013
Updated - Road Closure Schedule - Aug. 13, 2013
UPDATED - Road Closure Notice - Aug. 8, 2013
August Road Closure Notice - Aug. 1, 2013
Updated Road Closure Notice - July 22, 2013
SBGS Road Closure Map - July 18, 2013
Project Fact Sheet
Detour map- January 11 - 18, 2011
Community Meeting Presentation- July 13, 2011
Community Meeting Presentation- September 30, 2010
Community Meeting Presentation- March 31, 2010
Street Closure and Community Meeting Notice- January 9, 2012
Community Meeting Notice- July 13, 2011
Temporary Crossing Closures - Scott Street & South Linden Avenue

First Avenue Cul-de-sac Notice
Scott Street Night Work Notice
Temporary Station Night Work Notice

Find out what's happening in San Brunowith free, real-time updates from Patch.

Lead Agency: Caltrain

Contractors: Granite Construction Company

Project Limits: South Linden Avenue to San Felipe Avenue

Construction Cost: $155 million
(SMCTA: $92.5 million; State: $55.9 million; Federal: $6.6 million)

Began Construction: November 2010

Completed Construction: Tentatively scheduled for Spring 2014

For additional questions or concerns regarding the construction project, please contact our dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com. For questions about Caltrain service, please contact 800.660.4287.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?

More from San Bruno